Setting production rates in the mobile app

Learn how to set production rates in the Duranta mobile app, so Duranta can calculate how many hours the work you're estimating will take.

A production rate tells Duranta how much work one worker does in an hour, for example 100 feet of hedge per hour. Duranta uses it to work out how many hours a job takes, and your hourly price to work out what it costs.

Open your services

Tap More → Favorites → Services. Open a service, or tap + to create one.

Charge by the hour

Tap the unit next to Price and choose per hour. Then enter your hourly price.

Enter the production rate

Under Time per worker, tap the unit and choose a rate under Rates, such as sq ft per hour, acre per hour, cu yd per hour or ft per hour.

Enter how much one worker does in an hour, for example 100 ft per hour. Then tap Save.

💡 If the service uses materials, tap Material under Additional components to add them.