Use Scheduling to turn sold work into scheduled jobs with a date, time, crew, and duration.
You can manage work orders from the list, calendar, or routes view, then track what is scheduled, completed, skipped, canceled, or ready to invoice.
Where to find Scheduling
Open Scheduling from the left sidebar.
Scheduling has three tabs:
Tab | What it is used for |
Work orders | View every job, past and future. |
Routes | Plan each crew's route as a board or map. A route is one crew's jobs for one day. |
Calendar | View scheduled work by day, week, or month. |
All scheduling times are shown in your company’s time zone. The Scheduling header shows the city and time zone, such as Chicago · CDT. Hover over it to see the full description.
You can set your company time zone in Account Settings.
What is a work order?
A work order is one visit to one property.
It includes who the work is for, where it happens, when it is scheduled, how long it should take, which crew is assigned, and what work needs to be done.
You can create a work order from the Work orders tab or directly from the calendar by clicking an empty time slot.
A work order can include:
Work order number
Client and location
Work order date
Start time
Job duration
Status
Services
Crew
Materials
Equipment
Notes and images
Work order number
Duranta assigns a work order number automatically.
You can also use an optional prefix, such as WO.
The work order number can be edited.
Job duration
Job duration supports different units, including:
Minutes
Hours
Days
Weeks
Months
Durations can include decimals, except when the unit is minutes. For example, you can enter 1.5 hours.
Work order statuses
Status | Meaning |
Scheduled | The work order has a date and is ready to go. |
Upcoming | A future visit in a recurring series. |
In progress | The work is currently being done. |
Completed | The work is done. |
Invoiced | The invoice for this work has been sent. Duranta sets this automatically when an invoice converted from the work order is sent. |
Canceled | The visit was called off. |
Skipped | This visit was skipped, but the recurring series continues. |
You can change the status from a work order’s … menu.
You can also update statuses in bulk from the Work orders list.
Recurring work orders
Use Make recurring when a work order repeats.
Recurring options include:
Frequency | Repeats |
Daily | Every day |
Weekly | Every week |
Biweekly | Every 2 weeks |
Monthly | Every month |
Yearly | Every year |
Custom | A custom repeat pattern |
Calendar | Only on specific dates you choose |
After you choose a schedule, Duranta shows it as a plain-English summary.
For example:
Work orders are scheduled every 2 weeks, starting 14 April.
Review this summary before saving to make sure the pattern is correct.
End date
Duranta fills in an End date 364 days after the first visit. Change it to when the work should stop. You can pick an earlier or a later date, but you can't remove the end date. A series can have up to 365 visits, so how far out it can go depends on the frequency: about a year for a daily job, around seven years for a weekly one.
Duranta adds the end date to the schedule summary:
The schedule ends on 13 April.
If the end date allows more than 365 visits, Duranta shows: A series can have at most 365 visits. Pick an earlier end date.
The first visit uses the status you set. Future visits are created as Upcoming. When you save, Duranta creates every visit in the series at once, so they all show in the list and on the calendar straight away. To change the whole series later, open one of its visits and click Edit recurring template. The recurring template is the schedule and details every visit is made from. Saving it rebuilds the upcoming visits, so changes made to individual upcoming visits are replaced.
Custom recurring schedules
Choose Custom to create your own repeat pattern.
You can set:
Repeat every — choose the interval and unit, such as every 3 weeks or every 2 months
On these days — for weekly schedules, choose specific weekdays
For example, you can create one recurring work order that repeats every week on Monday, Wednesday, and Friday.
Calendar recurring schedules
Choose the Calendar frequency (not the Calendar tab) when the work does not follow a regular pattern.
Use this for seasonal visits or a specific list of agreed dates.
To use Calendar scheduling:
Choose Calendar.
Click Add date.
Add each visit date.
Review the selected dates.
Save.
Duranta requires at least one selected date.
If no dates are added, Duranta shows:
Add at least one date for this work order to repeat on.
Monthly schedules
Monthly schedules repeat on the same day of the month.
If you choose a date that does not exist in every month, such as the 31st, Duranta schedules shorter months on the last day of the month.
Duranta explains:
If a month doesn’t have 31 days, the work order is scheduled on the last day instead.
Skip, cancel, or end a recurring series
For recurring work orders, you can skip one visit or end the whole series. On the Day calendar or the Routes board, hover over a job and open its ⋮ menu to find Skip this visit, Cancel and End series.
Action | What happens |
Skip this visit | Skips one visit. If it is on a route, it stays there marked as Skipped. |
Cancel | Cancels the visit. If it is on a route, it stays there marked as Canceled. |
End series | Ends the series. Later visits are removed and no new ones are created. Past visits are not affected. |
The practical difference: Skip passes over one visit and the series carries on, while Cancel calls the visit off.
Both stay on the route, so the crew can see what was planned. Hide them with the View menu (see Show or hide schedule items below).
When ending a series, you can choose whether to skip the current visit or keep it scheduled.
Duranta explains:
The series ends on 20 May. Later visits are removed and no new ones are created. Past visits are unaffected.
Reschedule a work order
Use Reschedule from the work order’s … menu.
Before saving, Duranta explains what will happen.
For example:
Green Crew has a route on 20 May — the job will join it.
Or:
No route on 20 May — the job moves to Unassigned.
For recurring work orders, Duranta also warns you if the series already has a visit on that date.
Work orders list
The Work orders table shows:
Work order number
Client name
Property
Service date
Start time
Day
Assigned crew
Recurring status
Status
Updated at
You can search across the table, and filter from the column headers by client, service date, day of the week, assigned crew (including Unassigned), recurring and status. The table opens on this month’s work orders: change or clear the Service date filter to see others. Next to the presets, Custom lets you set your own From and To dates.
You can also select multiple rows and take bulk actions.
Bulk actions include:
Assign crew
Change status
Convert to invoice
Delete
If you assign a crew and that crew does not have a route on that day, Duranta creates a route automatically.
Canceled and skipped work orders stay on their routes, marked Canceled or Skipped.
Deleting work orders is permanent. If selected work orders are on routes, Duranta tells you before deleting.
Convert work orders to invoices
Select completed work orders and choose Convert to invoice.
If you select multiple work orders across different clients, you can choose how invoices are created:
Option | What it does |
Merge into one invoice per client | Combines each client’s selected services and notes into one invoice. |
Create separate invoices | Creates one invoice per work order. |
Duranta creates draft invoices so you can review them before sending. Once an invoice is sent, the work order moves to Invoiced, and View converted invoice in its … menu opens the invoice.
If a work order is not marked Completed, Duranta asks you to confirm before billing it.
Calendar views
The Calendar tab has three views:
View | What it shows |
Month | The month at a glance, with counts per day and unassigned jobs. |
Week | Each crew's week, with scheduled and completed counts and an Unassigned row. Turn on List routes vertically to see the week as a day-by-hour grid, with a Crew routes panel to show or hide each crew. |
Day | Each crew's route by the hour, with the total planned time in each route's header, blocked time and the current time line. Jobs that overlap sit side by side. |
Day view:
Week view:
Month view:
Build the day by dragging
In the calendar, you can drag work to schedule and adjust it.
You can:
Drag a job onto a crew’s route to assign it
Drag a job to another route to move it
Drag a job off a route to make it unassigned
Drag the edge of a job to change its duration
Click an empty time slot to create a work order or add blocked time
After moving a job, Duranta confirms the change.
For example:
WO-1042 moved to Green Crew’s route at 9:00 AM.
If you drop a job outside the crew’s route hours, Duranta warns you:
This job is outside the route’s hours
Block time
Use blocked time for time that is not a job, such as lunch, fuel stops, shop time, or equipment pickup.
Blocked time includes:
Label
Start time
End time
Blocked time belongs to a crew’s route. It cannot be dropped into the Unassigned column.
Blocked time appears in day and week views and can be dragged in either view.
Show or hide schedule items
Use the View menu to control what appears on the schedule.
You can show or hide:
Cancelled visits
Skipped visits
Archived routes
Hidden items are counted on the View button, so you can tell when something is hidden.
Share a work order
Use Preview to see the customer-facing version of a work order.
From Preview, you can:
Use Preview as customer
Print the work order
Share the work order link
When you share a work order, Duranta publishes a link you can copy.
If you edit the work order after sharing it, the recipient may see:
There is a newer version of this work order
They can use the link to open the latest version.
Activity
Each work order keeps an activity log.
Activity can include:
Created
Updated
Status changes
Crew assignments
Reschedules
Duration changes
Duranta also records where each change was made, such as:
Day calendar
Week calendar
Board
Map
Work orders list
Route dialog
This helps your team understand when and where schedule changes happened.